| 2) Location: Frederick City, Md.
Contract work consisted
of installing air conditioning to a Church complex, beginning with the large
sanctuary, without effecting the aesthetics and historic nature of the church.
The construction means and methods solution was to scaffold the entire area
and demolish all necessary existing structural work and finishes such as mill
work, plastering and masonry. After installation of the mechanical systems,
all features were reproduced to the exact original conditions in order for the
completed work to appear as if nothing had been disturbed.
|
 |
 |